We turn complex
problems to easy solutions

December 2022
Merry Christmas
October 2022
Demolition Lidingö bridge
September 2022
Quay for PEAB
August 2022
Open Bookings 2022/2023
May 2022
Platform, towercrane
May 2022
Master. EMS and GE
February 2022
OHLA subway tunnel
January 2022
Nestor overhaul
2022
December 2022
Merry Christmas

October 2022
Demolition Lidingö bridge

September 2022
Quay for PEAB

August 2022
Open Bookings 2022/2023

July 2022
Salmon eye

May 2022
Platform, towercrane

May 2022
Master. EMS and GE

May 2022
Loading winches

April 2022
Survey

March 2022
Tugboat Arne

February 2022
OHLA subway tunnel

January 2022
Nestor overhaul

January 2022
Armands Berze

2021
December 2021
PEAB and Aarsleff

November 2021
Preparation for OHLA

October 2021
Re-class Hermes to Master

August 2021
Skanska Lock Gate

July 2021
Transport from Norway

July 2021
North Carrier first trip

July 2021
Float off lock channel

June 2021
EMS and GE Energy

February 2021
Norrströmsbron

2020
December 2020
Open bookings 2020/2021

November 2020
Extended COOP with SCA

November 2020
25 concrete platforms

October 2020
Transformator 370 ton

October 2020
Extended Quay deck

October 2020
Jack Up in Kiruna

October 2020
Delivery Lifting devices

September 2020
North Carrier renovated

September 2020
Nord Stream II

August 2020
Beams transportation

August 2020
Transportable Jack up

July 2020
Lidingö Bridge pile work

July 2020
railway bridge demolition

July 2020
Slussen Stockholm

May 2020
Lidingö bridge foundation

May 2020
Fassi 60TM on Carrier 013

May 2020
Supporter 4

March 2020
Getingmidjan demolition

2019
October 2019
Temporary bridge Lidingö

October 2019
Carrier 16 in Ålesund

September 2019
test in Swinoujscie

September 2019
Extended fairway

August 2019
Working pontoon Carrier 4

August 2019
Carrier 8 Semisubmersible

July 2019
Herakles sold

June 2019
To Fredrikshamn float off

June 2019
Upgrade North Carrier

April 2019
Mounting roof

April 2019
Concrete elements

March 2019
Aarsleff production

March 2019
New RoLo Vessel

February 2019
Icebreaking tour February

January 2019
Launching floating concre

2018
December 2018
7500 tons on Carrier 16

December 2018
Icebreaking tour December

November 2018
Carrier 16 in action

September 2018
Nuuk Bridge Installation

August 2018
Nuuk Bridge Departure

July 2018
Nuuk Bridge Construction

June 2018
Shipment of Shipsections

May 2018
Accommodation barge

January 2018
Polar Explorer on duty

2017
December 2017
Bridgeproject Finland

November 2017
Polar Explorer Upgrade

August 2017
Transport Shipsloader

June 2017
Conversion of Carrier 7

May 2017
Lodbrok Lifting vessel

April 2017
Transport 13 000 tons

February 2017
Bridge and floating quay

January 2017
Transport Bridgesections

2016
December 2016
Expanded fleet

December 2016
Extended co-operation
.JPG)
November 2016
Offshore construction

November 2016
Dismantling bridge

September 2016
15 000 tons foundations

August 2016
Transport accommodations

June 2016
Transportation Timber
.jpg)
May 2016
Viktor

April 2016
Herakles Continues duties

March 2016
Carrier 16 Upgrade

February 2016
Carrier 7 floating quay

January 2016
New Company Name

2015
December 2015
Drydock

November 2015
Steeringhouse

October 2015
Quay for 1000 apartments

October 2015
Project completed

September 2015
Conversion two barges

August 2015
Gas baloons on fire

August 2015
Upgraded performance

July 2015
Insallation 3 ramps

July 2015
De-mobilisation

June 2015
Bridge sections

June 2015
Passenger gangways

May 2015
840 Concrete Elements

April 2015
Timbertransports
.JPG)
March 2015
Transportable wood-plant

February 2015
Emergency Vessel

January 2015
Removing dyktalbs

2014
December 2014
New counterweight crane

November 2014
Continue breaking ice

October 2014
New pontoon

September 2014
Elements to Värtahamnen
.jpg)
August 2014
Workingboat Aramis

July 2014
Removing MET-mast
.jpg)
June 2014
Final Design

May 2014
960 pieces
.jpg)
April 2014
New quay

March 2014
New contract ETV

March 2014
5 years contract

2013